Member Project Spotlight

Total Movements, India Delivers Critical Heavy Engineering Components for a Reputed Customer

|
Total Movements handled a door-to-door shipment from Italy's factory to India's delivery site carried about 700FRT of ODC cargo, with its heaviest piece weighing 66MT.
The entire cargo was planned to be loaded and shipped out of the Italian Port. However, due to various infrastructural upgrades en route and the holiday season, Road Permits were quite delayed, affecting the overall project schedule.
|

Since our team monitored these developments daily, we understood that we needed to execute our “Plan B”.Our team discussed with the various stakeholders involved in the shipment to start the execution using the alternate route/shipping plan.

While it was a challenge to arrange alternate permits/booking space on the vessel (in the current scenario) at the last minute, with agile actions, our team was able to achieve this movement on schedule for the client.